Voluntary Cleanup Status
Cherokee has been participating in the CDPHE’s Voluntary Clean
Up Program (VCUP) and have divided the site into nine different parcels
VCUP 1 – Vanderbilt Lake
- Completed remedial actions
- Received the approved no further action determination
from CDPHE on 8/3/05
VCUP 2 – Separated into A and B
- No remedial activities planned on 2A as there is little
contamination
- Received the approved no further action determination
from CDPHE on 9/15/05
- Investigations on 2B including soil sampling and groundwater
wells began in the fall of 2005
VCUP 3
- VCUP application submitted at the end of August 2005
- Do have total petroleum hydrocarbons and chlorinated solvents
in the area – there were storage tanks on this parcel
- Completed additional soil characterization in July 2005
- Will demolish building 26, excavate impacted soils and
do enhanced bioremediation for groundwater impacts
VCUP 4
- VCUP application submitted at the end of September 2005
and approved 11/15/05
- Found benzene in the soil with minor impacts to groundwater – there
was a gas station on this parcel
- Remediation has started and will use enhanced bioremediation
to cleanup
VCUP 5
- Completed excavation of impacted soils
- Completed post remediation monitoring – all TCE
at property boundary is below the MDL except for two wells
- Another round of groundwater monitoring done in Sept.
2005
- Did install wells next to the CML since that is the direction
the water is flowing and most were non-detect for TCE
- Submitted a no further action determination in April 2006 – awaiting
approval
VCUP 6
- No activities completed or planned
- No know source areas on parcel
VCUP 7
- Installed 2 groundwater monitoring wells
- VCUP will be tied to building demolition – as can’t
get to source area as it’s under the building
- Tested the other side of Broadway and had non-detects;
Gates did not find anything on their property in this area
|